Skim the whole map before walking the trail. In 2026, successful PDM_2002001060 candidates start with the full Nokia CPM outline and the 215 practice questions from TorrentExam, then drill the difficult points they marked along the way.
Nokia PDM_2002001060 Exam Syllabus Topics:
| Section | Objectives |
|---|---|
| Topic 1: Project Execution & Monitoring | - Team management and communication - Cost adherence, earned value and KPI tracking - Change control and issue resolution |
| Topic 2: Project Initiation & Business Case | - Project charter and stakeholder identification - Business case definition and approval |
| Topic 3: Project Closure & Handover | - Financial closure and lessons learned - Contract acceptance and site quality review |
| Topic 4: Nokia-Specific Processes & Tools | - Vendor management and back-to-back principles - IPM, PCA, PARD and P-SQI metrics |
| Topic 5: Project Planning & Scope Management | - Risk, quality and procurement planning - Scope definition and work breakdown structure - Schedule, resource and cost planning |
Nokia PDM_2002001060 Exam: Read Before You Buy
Nokia CPM is an official Nokia exam, catalogued under exam code PDM_2002001060. Passing it awards the Nokia Certified Project Manager (CPM) certification at the Professional level. It also connects with Nokia Project & Portfolio Management Certification. It is built for candidates with ambitious aims, and the credential it grants is recognized accordingly.
Nokia CPM spans 5 official domains, led by Nokia-Specific Processes & Tools, Project Initiation & Business Case, and Project Planning & Scope Management. The complete outline sits above; before getting down to business, look through the whole contents quickly so every later practice session has context.
The Nokia CPM exam presents 213-215 questions within 60 minutes. A practical tip from successful candidates: mark the most difficult questions during practice, exchange notes on them with friends, and repeat them until they stop being difficult. The TorrentExam engine makes that loop fast, and the clock stops being a threat.
Passing Nokia CPM requires Not officially published, and official registration costs Not officially published. Retakes bill the full Not officially published again, so verify readiness before booking: when your TorrentExam practice scores clear the requirement repeatedly, including on questions you once marked as difficult, you are ready.
Basic project management knowledge; no mandatory official prerequisites
Requirements change from time to time, so confirm the current conditions before registering on the official exam page.
Nokia CPM registration is handled through the official channels below.
When you schedule, note that the exam is delivered Online proctored or authorized test center.
Nokia recommends the following training for Nokia CPM candidates.
Combine any training with the 215 practice questions in the TorrentExam PDM_2002001060 package; one or two focused days of repeated practice after a course is often what locks the knowledge in.
Yes, a free demo of the Nokia CPM questions is available before purchase. Afterward, you can track freshness by the updating version number on the website, and whenever questions change we instantly email the details to you, free for 365 days. We even keep sending the latest questions after you pass, so you can follow every tiny change. After expiry, extending updates costs 50% of the regular price.
Your purchase carries a 100% money-back guarantee under clear conditions. Take the Nokia CPM exam within 60 days of purchase; if you fail, you may claim a full refund, provided the exam matches your product. Attempts within 3 days of purchase are ineligible, as are downloaded-but-unused products, free materials, and expired orders; the candidate name must match the payer name. Submit a scanned enrollment slip and the official Score Report PDF within 2 days of the exam, and claims are processed within 7 days. Alternatively, exchange for two other exam products of equal value, free, keeping the update service on your original purchase.
Delivery is instant: download after ordering, with an automatic email arriving within one minute. If nothing arrives within 2 hours, do not forget to check your junk mailbox, then contact customer service. Installation is unlimited across your computers.
Nokia CPM Sample Questions:
What is an example of NCC?
- A. Extra costs for replacement of products under warranty.
- B. Extra costs for root cause analysis of unexpected product failure.
- C. Extra costs for commissioning spares.
- D. Additional delivery costs for retrofitted products.
Correct Answer: B 🗳️
What is NOT a key element for the lower level WBS structure set up in SAP from a cost and progress manager perspective?
- A. Ability to execute customer orders.
- B. F&C requirement.
- C. Cost reporting capability for identified project scope.
- D. To support IPM setup.
Correct Answer: B 🗳️
A subcontractor raises a change request for extra work on a specific site. The project
manager requests an entry to the IPM CR module. This is:
- A. the recommended process because only site level changes are managed in the IPM CR module.
- B. the incorrect process because all changes should be logged into 4C CCR.
- C. the recommended process because IPM supports site level changes very well, especially with the RTI capability.
- D. the incorrect process because the prudency principle should be followed and the customer order should be received first.
Correct Answer: C 🗳️
What is the definition of project Risk Management?
- A. To manage risks that will enable Nokia to profitably grow the business, while having a basic understanding of the risks and responses required.
- B. To take risks that will enable Nokia to profitably grow the business while having a thorough understanding of the risks and responses required for its success.
- C. To avoid risks that would damage the desired growth in sales and profitability while taking all opportunities to positively influence customer satisfaction.
- D. To maximize the probability and consequences of positive events and minimize the probability and consequences of adverse events to project objectives.
Correct Answer: D 🗳️
What of the following cost components is NOT included in the CBL?
- A. Non conformance costs.
- B. Base costs.
- C. Sub-contracting costs.
- D. Risk contingency.
Correct Answer: A 🗳️
Viewing page 1 out of 43 pages.
Viewing questions 1-5 out of 215 questions.