NEW QUESTION # 25
What general ledger accounts receive postings when performing the goods receipt?
Note: There are 2 correct answers to this question.
- A. Consumption account
- B. GR/IR account
- C. Tax Account
- D. Vendor reconciliation account
Answer: A,B
NEW QUESTION # 26
What occurs when planning an internal project activity?
- A. Costs are recorded.
- B. Purchase requisitions are generated.
- C. Service is performed.
- D. Resources are committed.
Answer: D
NEW QUESTION # 27
Which of the following applies to Sales and Distribution enterprise structures?
Note: There are 3 correct answers to this question.
- A. A sales organization can only be assigned to one company code.
- B. A division can be assigned to more than one sales organization.
- C. A distribution channel can be assigned to many sales organizations.
- D. A division can only be assigned to one sales organization.
- E. A sales organization can be assigned to more than one company code.
Answer: A,B,C
NEW QUESTION # 28
What types of procedures may be used to perform a cross-plant stock transfer?
Note: There are 3 correct answers to this question.
- A. Slotting and rearrangement
- B. Material requirements planning
- C. Stock transport order without delivery
- D. Two-step procedure
- E. One-step procedure
Answer: C
NEW QUESTION # 29
What type of document is generated for an external network activity?
- A. Purchase requisition
- B. Reservation
- C. Production order
- D. Sales order
Answer: A
NEW QUESTION # 30
To what object can you settle an internal order?
- A. Fixed asset
- B. Profit center
- C. Statistical key figure
- D. Equipment
Answer: A
NEW QUESTION # 31
What information do you maintain for a general ledger account on company code level?
- A. Account group
- B. Account type
- C. Account currency
- D. Account number
Answer: C
NEW QUESTION # 32
Which SAP Fiori application types use SAP HANA capabilities directly?
Note: There are 2 correct answers to this question.
- A. Fact sheet
- B. Transactional
- C. SAP GUI for HTML
- D. Analytical
Answer: A,D
NEW QUESTION # 33
What is the purpose of using a Work Breakdown Structure (WBS)?
Note: There are 3 correct answers to this question.
- A. To schedule warehouse tasks
- B. To manage equipment
- C. To allocate budgets
- D. To define responsibilities
- E. To evaluate aggregated data
Answer: C,D,E
NEW QUESTION # 34
In a warehouse, what represents the physical location where the goods are stored?
- A. Storage bin
- B. Storage section
- C. Storage location
- D. Pallet
Answer: A
NEW QUESTION # 35
Which business process activities create a Financial Accounting (FI) document?
Note: There are 3 correct answers to this question.
- A. Create a sales order
- B. Transfer stock from storage location to storage location
- C. Execute a depreciation run
- D. Transfer stock to another company code
- E. Post goods issue to a production order
Answer: C,D,E
Explanation:
These activities result in financial postings that impact the general ledger, thus requiring the generation of a Financial Accounting (FI) document:
Transfer stock to another company code: Because this involves moving value between two distinct legal entities, it triggers intercompany accounting and tax postings.
Post goods issue to a production order: This activity consumes raw materials or semi-finished goods, reducing inventory value and increasing production costs.
Execute a depreciation run: This periodic task calculates and posts asset depreciation, directly impacting the balance sheet (accumulated depreciation) and the income statement (depreciation expense).
NEW QUESTION # 36
What action assigns actual costs to a project?
- A. Saving a purchase order
- B. Material withdrawal from stock
- C. Releasing a project budget
- D. Material availability check
Answer: B
Explanation:
In SAP Project Systems, actual costs are recorded when resources are consumed and physically leave the warehouse or when services are performed.
Material withdrawal from stock: This action (also known as a Goods Issue) triggers the posting of actual costs because it represents the actual consumption of inventory for the project's use.
Financial Impact: At the moment of withdrawal, the system generates a controlling document that updates the project's actual cost totals.
Why other options are incorrect
❌ B. Saving a purchase order: This only creates a commitment (planned future cost). Actual costs are not assigned until a goods receipt or vendor invoice is posted against that order.
❌ C. Material availability check: This is a planning and scheduling step to ensure materials are available. It does not involve any financial transactions or cost postings.
❌ D. Releasing a project budget: This action makes funds available for use but does not represent an actual expenditure or resource consumption.
NEW QUESTION # 37
You purchase raw materials with a purchase order against a cost center. During which process step are financial accounting documents posted?
- A. Save purchase order
- B. Inbound delivery to warehouse
- C. Approval of purchase requisition
- D. Post valuated goods receipt
Answer: D
NEW QUESTION # 38
For which object do you plan activity prices?
- A. WBS element
- B. Internal order
- C. Work center
- D. Cost center
Answer: D
NEW QUESTION # 39
Which object is created to report on market characteristics, such as customer, product, and region?
- A. Profit center
- B. Profitability segment
- C. Segment
- D. Sales organization
Answer: B
NEW QUESTION # 40
What must you do in a purchase order to purchase a material for a cost center?
- A. Enter an account assignment category.
- B. Enter a storage location.
- C. Enter an activity type for the cost center in the purchasing document.
- D. Enter a purchase order item category.
Answer: A
NEW QUESTION # 41
What objects are used to create a Purchasing Info Record?
Note: There are 3 correct answers to this question.
- A. Vendor
- B. Material master
- C. Purchasing organization
- D. Company code
- E. Purchasing group
Answer: A,B,C
NEW QUESTION # 42
In the enterprise structure, what Human Resources organizational element is assigned directly to a company code?
- A. Position
- B. Organizational unit
- C. Personnel area
- D. Infotype
Answer: C
NEW QUESTION # 43
What data must be linked to a cost center to derive segment accounting?
- A. Cost center category
- B. Profit center
- C. General ledger account
- D. Controlling area
Answer: B
NEW QUESTION # 44
What is the result of converting a planned order? Note: There are 2 correct answers to this question.
- A. A purchase order
- B. A purchase requisition
- C. A production order
- D. A planned independent requirement
Answer: B,C
NEW QUESTION # 45
What activities can a manager complete using Manager Self-Service?
Note: There are 2 correct answers to this question.
- A. Manage budget
- B. Enroll in benefits
- C. Enter time sheet
- D. Control costs
Answer: A,D
NEW QUESTION # 46
What is created when you post a valuated goods receipt for consumable materials?
- A. Vendor invoice document
- B. Controlling document
- C. Material ledger document
- D. Commitment
Answer: C
NEW QUESTION # 47
During the production order process, what steps can be executed via background processing?
Note: There are 3 correct answers to this question.
- A. Order settlement
- B. Order creation
- C. Order confirmation
- D. Order release
- E. WIP determination
Answer: A
NEW QUESTION # 48
What does a work center control?
Note: There are 2 correct answers to this question.
- A. Valuation of bill of material components
- B. Calculation of costs of work performed
- C. Release of production orders
- D. Availability of capacity
Answer: B,D
NEW QUESTION # 49
Which end-to-end business processes are included with SAP S/4HANA in the context of the Intelligent Enterprise? Note: There are 3 correct answers to this question.
- A. Design to build
- B. Source to pay
- C. Order to cash
- D. Request to service
- E. Record to report
Answer: B
NEW QUESTION # 50
......