NEW QUESTION # 22
In project management, a WBS element for accounting integration was created automatically.
What is used to calculate the planned costs of this WBS element?
NOTE: There are 3 correct answers to this question

  • A. Demand planned on project roles
  • B. Duration planned on project tasks
  • C. Staffing of work in the role
  • D. Work planned on project task

Answer: A,D


NEW QUESTION # 23
You want to confirm your work hours to tasks with the cross-Application time sheet (SAP CATS). When you enter the time sheet (CAT2) your list is empty.
What could be the reason for this?
NOTE: There are 2 correct answers to this question.

  • A. Your user is not assigned to a business partner
  • B. Your personal number is not assigned to a business partner
  • C. Your role and business partner are assigned to tasks that have the in process status
  • D. Your role and business partner are assigned to task that have the created status

Answer: B,D


NEW QUESTION # 24
You want to split the financial planning values of portfolio item into two different buckets.
How do you do this?

  • A. Enable the split of financial values for the item type
    * Assign the item to two bucket of the portfolio
    * Maintain factors to split financial planning of the item
  • B. Enable financial planning for multiple buckets
    * Assign additional buckets in financial planning
    * Maintain factors to split financial planning of the item.
  • C. Enable process change for multiple buckets.
    * Start process change to reassign the item two buckets
    * Maintain factors to split financial planning of the item
  • D. Enable the split of financial values for the item type.
    * Assign the item to two bucket of the classification hierarchy
    * Maintain factors to split financial planning of the item

Answer: D


NEW QUESTION # 25
What are valid breakdown period for financial planning in portfolio management?
NOTE: There are 2 correct answers to this question.

  • A. months
  • B. Weeks
  • C. Years
  • D. Days

Answer: A,C


NEW QUESTION # 26
Which of the following are valid breakdown periods for financial planning in Portfolio Management? Note: There are 2 correct answers to this question

  • A. 3 months
  • B. 10 days
  • C. 1 year
  • D. 2 weeks

Answer: A,C


NEW QUESTION # 27
What are prerequisites for using cross-Application time sheet (SAP CATS) to confirm In a project management project?
NOTE: There are 3 correct answers to this question.

  • A. The planned efforts is on the task
  • B. The role type must allow time recording with CATS
  • C. Accounting integration for this project is active
  • D. The project type must allow time recording with the CATS

Answer: C,D


NEW QUESTION # 28
One of the tasks of your project has subtasks. You wants to restrict time recording to the subtasks.
How can you achieve this in customizing?

  • A. Activate task hierarchies with summarization
  • B. Activate task hierarchies without summarization
  • C. Deactivate time recording for tasks
  • D. Deactivate the mirrored task indicator for the project type

Answer: B


NEW QUESTION # 29
What can you with roles in project management?
NOTE: There are 3 correct answers to this question

  • A. Define responsibilities for structure element
  • B. Enable resource management
  • C. Define decision makers for an approval process
  • D. Define responsibilities for structure element
  • E. Define authorizations for reporting

Answer: A,B,C


NEW QUESTION # 30
Which of the following are basic parts of SAP innovation management?
NOTE: There are 2 correct answers to this question.

  • A. Innovation office
  • B. Idea community
  • C. Mobile web app
  • D. Portfolio Review
  • E. Opportunity overview

Answer: A,B,C


NEW QUESTION # 31
What must you do before you can use multiple currencies in financial planning in portfolio management?

  • A. Define a subnet of currencies in project system
  • B. Select multiple currencies in the portfolio definition
  • C. Select multiple currencies in the portfolio item
  • D. Define a subnet of currencies in portfolio and project management

Answer: A


NEW QUESTION # 32
You are planning resources.
Which period types are available?
NOTE: There are 3 correct answers to this question.

  • A. Monthly
  • B. Hourly
  • C. Weekly
  • D. Daily

Answer: A,C


NEW QUESTION # 33
What is the PR/PLAN_INI_PREP report used for?

  • A. To transfer costs from accounting objects to PPM
  • B. To upload financial data from Microsoft Excel
  • C. To create financial and capacity categories and groups based on customizing
  • D. To transfer recoded time from CATS to PPM

Answer: C


NEW QUESTION # 34
In project management, what data can be copied from a project template during creation of a new project?
NOTE: There are 3 correct answers to this question.

  • A. Dates
  • B. Checklist
  • C. Project structure
  • D. Authorizations
  • E. Responsible organizational unit

Answer: C,D,E


NEW QUESTION # 35
When you create an item from an initiative, which of the following objects are authorizations inherited from?
NOTE: There are 3 correct answers to this question

  • A. Project management project
  • B. Project system project
  • C. Portfolio
  • D. initiative
  • E. Parent bucket

Answer: C,D,E


NEW QUESTION # 36
Which of the following multi-currency scenario are supported?
NOTE: There are 2 correct answers to this question

  • A. Multiple planning currencies can be used in one bucket
  • B. Item currency can be inherited from the assigned bucket
  • C. Bucket in a portfolio can use different currencies
  • D. Items In a bucket an only use bucket currencies

Answer: B,C


NEW QUESTION # 37
What is a prerequisite for using role charts in project management?

  • A. The demand of a role must be distributed over a number of periods
  • B. A graphic profile is assigned to the project type
  • C. The demand of a role must have been updated according to tasks
  • D. A graphic profile is assigned to the role type

Answer: A


NEW QUESTION # 38
You want to add a report to the side panel of the item detail screen. The new report should display the upto-date financial planning values for the item.
Which reporting tool do you use?

  • A. BI report
  • B. Evaluation
  • C. Portfolio dashboard
  • D. Business Context Viewer (BCV)

Answer: D


NEW QUESTION # 39
What are dashboard alerts calculations based on?

  • A. Percentage values
  • B. Business Add-in (BAdi) implementation
  • C. Numeric values (Specified range)
  • D. The status fields

Answer: C


NEW QUESTION # 40
You have created a role in project management but the role is not displayed on the fast entry screen.
What could be the reason for this?

  • A. The role has the staffing in process status
  • B. The flexible Assignment indicator is active in role type customizing
  • C. The Distribution indicator is active role type customizing
  • D. The role has the staffing in preparation status

Answer: D


NEW QUESTION # 41
Which method can you use to update multiple values simultaneously in capacity planning for portfolio management?

  • A. XML upload
  • B. Distribution function
  • C. Mass update
  • D. Drag and drop

Answer: B


NEW QUESTION # 42
Bucket A contains items and current located in bucket P1.
How do you move bucket A including the items to bucket p2.

  • A. Move all items from bucket A to bucket p2.
    Move the empty bucket A to p2
    Copy all bucket A items from bucket p2 to bucket A
  • B. Select bucket A from the bucket dashboard
    Change the parent bucket field from P1 to P2
  • C. Create a new bucket in bucket P2
    Move all items from bucket A to the new bucket
    Delete bucket A and rename the new bucket
  • D. Select bucket p2 in the move function as a target for bucket A
    Execute the move function

Answer: C


NEW QUESTION # 43
How can you connect an original file with a project management task?
NOTE: There are 2 correct answers to this question.

  • A. Upload the original file using integration to a third party documents management system
  • B. Use Document services to create a link to the original file
  • C. Create a link to a documents into record hierarchy that contains the file
  • D. Use the Create New Document function in project management and check in the file

Answer: C,D


NEW QUESTION # 44
Which data is transferred when you import a Microsoft project management?

  • A. Authorizations
  • B. Cost
  • C. Status reports
  • D. Task

Answer: D


NEW QUESTION # 45
Which objects can used to record times in Cross-Application Time Sheels (SAP Cats)?
NOTE: There are 3 correct answers to this question

  • A. Role
  • B. Checklist item
  • C. Phase
  • D. Task

Answer: A,D


NEW QUESTION # 46
......


The exam consists of 80 multiple-choice questions that must be completed within a time frame of 180 minutes. To pass the exam, candidates must score a minimum of 63%. The exam is available in multiple languages, including English, Spanish, French, German, Japanese, Korean, Portuguese, Russian, and Chinese.

 