PRINCE2 Agile Foundation Exam is the entry-level certification exam for the PRINCE2 Agile methodology. PRINCE2-Agile-Foundation exam is ideal for professionals who are new to PRINCE2 Agile and are looking to establish a solid foundation in this methodology. PRINCE2 Agile Foundation certification exam covers the basics of PRINCE2 Agile, including the principles, themes, and processes that are used in this methodology. By passing PRINCE2-Agile-Foundation exam, individuals can demonstrate their understanding of PRINCE2 Agile and their ability to apply this methodology in real-world projects.
NEW QUESTION # 55
Which is a purpose of the quality theme?
- A. To determine how the means of delivering products is communicated
- B. To assess any potential improvements to a product
- C. To define the specific conditions that enable a product to be usable
- D. To evaluate whether the project continues to be achievable
Answer: D
NEW QUESTION # 56
Which process can take place during a release review workshop?
- A. Managing a stage boundary
- B. Directing a project
- C. Controlling a stage
- D. Managing product delivery
Answer: D
NEW QUESTION # 57
Who needs to be aware that flexing what is delivered may affect the expected benefits of the project?
- A. The team manager and the senior supplier
- B. The team quality assurance and project support
- C. The project manager and the project board
- D. Customer subject matter expert and the supplier representative
Answer: C
NEW QUESTION # 58
Which statement about the 'protect the level of quality' target is CORRECT?
- A. It delivers the early realization of benefits
- B. It gives confidence on the progress of the project
- C. It is achieved by allowing enough time for testing
- D. It is achieved by using the same team members
Answer: A
Explanation:
Reference:
%20level%20is%20met
NEW QUESTION # 59
Which TWO statements about the supplier subject matter expert are CORRECT?
1) They provide a wider picture of the customer view.
2) They prioritize requirements at the detailed level.
3) They should be focused on the customer.
4) They ensure that the work is compliant with project standards.
- A. 1 and 4
- B. 1 and 2
- C. 2 and 3
- D. 3 and 4
Answer: D
NEW QUESTION # 60
What needs to happen when new detailed requirements are added to a timebox?
- A. The delivery milestones should be reviewed and re-planned
- B. Requirements of a similar level of effort should be removed
- C. Formal change control should be applied
- D. More people should be added to the delivery team
Answer: B
NEW QUESTION # 61
Which is a purpose of the 'managing product delivery' process?
- A. To agree on what is required for accepting, executing and delivering project work.
- B. To delegate day-to-day management of the project to the project manager
- C. To plan the delivery of the products before committing to significant expenditure
- D. To establish and deliver the project communications to the wider organization
Answer: A
NEW QUESTION # 62
What is an epic?
- A. The set of products handed over to the users
- B. A prioritized list of requirements to be delivered in a sprint
- C. A high-level user story that is quite broad or vague
- D. A detailed user story with high business value
Answer: C
NEW QUESTION # 63
What does velocity typically measure?
- A. Work packages completed by the team
- B. The number of timeboxes completed
- C. The rate of progress the team is making
- D. The speed that a minimum viable product is created
Answer: C
NEW QUESTION # 64
Which statement is CORRECT with respect to the management of risk using PRINCE2 Agile?
- A. It should always be carried out informally
- B. It should always be addressed during the daily stand-ups
- C. It should always be appropriate to the needs of the project
- D. It should always be carried out formally
Answer: C
NEW QUESTION # 65
What should be emphasized when tailoring the PRINCE2 Progress theme?
- A. Planning resources
- B. Monitoring what is being delivered
- C. Assessing the impact of risks
- D. Tracking time and cost
Answer: B
NEW QUESTION # 66
In Lean Startup, what is based on the concept of 'learn the most with the least effort'?
- A. A set of criteria to determine whether work can be started
- B. A structured, timeboxed event
- C. A minimum viable product
- D. A measurement of lead times
Answer: C
NEW QUESTION # 67
Which statement about the 'protect the level of quality' target is CORRECT?
- A. It is achieved by ensuring that all features are delivered
- B. It allows change at the detailed level to be handled dynamically
- C. It is unlikely to be achieved if incomplete user documentation is provided
- D. It avoids the use of extra people to improve progress during a timebox
Answer: A
NEW QUESTION # 68
Which statement about the 'embrace change' target is CORRECT?
- A. It re-establishes team dynamics when a new member joins the team
- B. It trades user stories for those of a similar size
- C. It degrades the performance of the features that are delivered
- D. It results in the late delivery of the minimum viable product
Answer: C
NEW QUESTION # 69
Which statement explains the PRINCE2 Agile behavior of 'exploration'?
- A. It seeks out feedback collaboratively from project stakeholders
- B. It uses the most effective channel to communicate information
- C. It empowers the project management team at the delivery level
- D. It displays the progress rate to everyone using burn-down charts
Answer: A
NEW QUESTION # 70
Which is NOT one of the core concepts of Lean Startup that apply to PRINCE2?
- A. To create a minimum viable product to manage uncertainty
- B. To build, measure, learn from your experiences
- C. To use empiricism, based on knowledge that comes from experience
- D. To fail fast, if you are going to fail
Answer: C
NEW QUESTION # 71
Which TWO project board responsibilities are specifically assigned to the senior user?
1) Demonstrating the achievement of benefits.
2) Specifying the needs of those impacted by the outputs.
3) Balancing business, user and supplier demands.
4) Ensuring that the project delivers value for money.
- A. 1 and 4
- B. 1 and 2
- C. 2 and 3
- D. 3 and 4
Answer: B
NEW QUESTION # 72
Which statement BEST describes the PRINCE2 Agile guidance for change?
- A. The executive should manage changes dynamically at the detailed level
- B. The delivery team should be authorized to make changes at the detailed level
- C. The delivery team should quickly approve changes to the project baseline
- D. The executive should approve delivery level changes to harness the benefits of positive change
Answer: B
NEW QUESTION # 73
Which statement about the 'keep teams stable' target is CORRECT?
- A. It results in the earth delivery of a minimum viable product
- B. It will lead to a lower cost of ownership
- C. It ensures that the level of quality is protected
- D. It is required in order to allow the team to self-organize
Answer: D
NEW QUESTION # 74
Which statement about quality tolerances for a product is CORRECT in an agile context?
- A. All quality criteria tolerance must be fixed
- B. All quality criteria should have zero tolerance
- C. Quality tolerances should be the same for all quality criteria
- D. Setting quality tolerance relies on prioritising quality criteria
Answer: D
NEW QUESTION # 75
Why are team working agreement produced?
- A. To ensure that the delivery team members comply with company policy
- B. To create structure so that the team manager can assess individual performance
- C. To evolve the effectiveness and behaviors of the self-organizing team by agreeing values
- D. To make the team rules visible to the project manager for monitoring purposes
Answer: C
Explanation:
Reference https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_126&showNav=true&expandNav=true
NEW QUESTION # 76
Which statement about the 'initiating a project' process is CORRECT?
- A. The process should take more time than usual for disruptive projects
- B. The project solution should be documented in detail in the project product description
- C. The initiation stage plan should form part of the project plan
- D. The impact of frequent releases on quality management should be assessed
Answer: D